St. Alban the Martyr

Phase II Roof Renewal — June 2020


This page is part of our project "Revealing St Alban's Hidden Heritage" supported by a grant from The National Lottery Heritage Fund, thanks to players of The National Lottery.


After a nine week pause due to precautions to slow the spread of Covid-19, work restarted on 1st June 2020 and by 3rd June stripping the tiles form the south aisle was complete, ready for inspection of the roof by the architect:

The south aisle stripped of tiles and sheeted 3 June 2020

Meanwhile the scaffolding at the west end was growing in height:

West end scaffolding 3 June 2020

And the contractors had started to stip the tiles from the north aisle roof:

Stripping tiles on the north aisle; another deck at the west end 5 June 2020

The west end scaffolding 8 June 2020

The following pictures are courtesy  our architect from of Hook Mason Ltd., who examined the aisle roofs and the west façade from the scaffolding on the 15th of June.

The south aisle roof with new protective sheeting 15 June 2020. Photo: Hook Mason Ltd.

The north aisle roof ready for inspection 15 June 2020. Photo: Hook Mason Ltd.

Inspection from the roof voids over the aisles had already shown that most of the roof timbers were sound. Stripping the roofs revealed only two small areas of decayed timbers needing replacement. One was on the north aisle, where a rafter laid in a recess in the top of a cross wall within the roof space had rotted. This is directly below the spout of a downpipe the carries half of the rainwater from the north side of the nave roof, so even a slight defect in the roof here will have led to repeated soaking, while because the rafter was encased in the wall there will have been minimal air circulation to dry it out.

Site of decayed rafter in the north aisle roof 15 June 2020. Photo: Hook Mason Ltd.

The other decayed timber was at the west end of the South Aisle, where a rafter and tilting fillet had rotted.

Decayed timber at the west end of the south aisle roof 15 June 2020. Photo: Hook Mason Ltd.

The small amount of carpentry repairs needed was within what had been allowed for in the priced specifications.

However, the rose window was found to need additional work, including the replacement of several damaged pieces of glass, repainting of ironwork and clearance of pigeon guano.

Broken glass and pigeon droppings in the Rose Window 15 June 2020. Photo: Hook Mason Ltd.

There is also a need for some extra pointing, including at the bottom of the wall of the external balcony above the rose window that gives access to the interior of the Nave roof.

After the architect had inspected the aisle roofs, the scaffolders were able to continue to raise the scaffolding towards the Nave roof. By the 22nd of June the supports were in place on the North Aisle roof ready to raise the scaffolding, while the scaffolding at the end of the North Transept had already reached full height.

West end and north side scaffolding 22 June 2020

By the end of the week the scaffolding had reached the roof along the north side of the nave.

West end and north side scaffolding 26 June 2020

On June the 30th the roof of the North Transept we being stripped of tiles and battens.

Stripping the North Transept 30 June 2020

Read about the progress of the work during July here: http://www.saintalban.co.uk/restoration/roofrenewal2/july/.

Or return to March to May here: http://www.saintalban.co.uk/restoration/roofrenewal2/marchtomay/